The concession's advance sustainability scopes are one of the prime reasons that locked the deal for ADNOC. (Image source: Adobe Stock)

In its first strategic investment in Mozambique, ADNOC has acquired 10% of Galp’s interest in the Area 4 concession of the Rovuma basin in Mozambique

The acquisition will allow ADNOC a share of the liquefied natural gas (LNG) produced from the concession.

With the operational Coral South Floating LNG (FLNG) facility, the planned Coral North FLNG development and the planned Rovuma LNG onshore facilities, the concession has a combined production capacity of more than 25 mn tonnes per annum. It is one of the world’s largest gas discoveries in 15 years. 

A one-of-a-kind facility in Africa, the Coral South development is currently in operation, with a production capacity of up to 3.5 mtpa of LNG. Once up and running, the Coral North development is capable of adding another 3.5 mtpa of LNG to that. It will have a FLNG facility to process and liquefy natural gas for export. 

The Coral south development is already yeilding vegetable oil to serve as feedstock in Eni's biorefineries

The modular, electric-drive design of the 18-mtpa Rovuma Onshore LNG development is capable of challenging industry standards when it comes to carbon intensity reduction from LNG production. 

The concession's advance sustainability scopes are one of the prime reasons that locked the deal for ADNOC, which aims to achieve a just transition-driven net zero by 2045. 

Integrated global gas business 

Musabbeh Al Kaabi, ADNOC executive director for low carbon solutions and international growth, said, “For over fifty years, ADNOC has been a reliable and responsible global provider of LNG and we are building on this role with this landmark investment in the world-class Rovuma supergiant gas basin in Mozambique as we deliver on our international growth strategy. Natural gas plays an important role to meet growing global demand with lower emissions compared to other fossil fuels and this acquisition supports our efforts to build an integrated global gas business to ensure we continue providing a secure, reliable and responsible supply of natural gas.”

 

 

 

 

 

The facility will switch to natural gas operation when the natural gas pipeline will be commissioned. (Image source: Wärtsilä)

Technology group Wärtsilä has signed a 10-year Operations and Maintenance (O&M) Agreement for a captive power plant providing the energy for a Nigerian cement producing facility.

The new cement plant is owned by Mangal Industries and is located in Kogi State, Nigeria. The order was booked by Wärtsilä in Q2, 2024.

The power plant is critical to the facility’s cement production since the site is remotely located with limited access to the electricity grid. It operates with five Wärtsilä 34DF dual-fuel engines delivering an output of 50 MW. The O&M agreement is designed to ensure that the facility can reliably maintain its cement production target of three million metric tons per year.

“We are reliant on the power plant for our operations. This is why we have opted to take advantage of Wärtsilä’s depth of experience and know-how to run and maintain the power plant. Not only will the agreement provide the assured reliability we need, but it also gives us cost predictability,” said Fahad Mangal, Managing Director, Mangal Industries Limited.

The ten-year agreement starts immediately as the facility commences operations in Q2, 2024, running on liquid fuel initially. The facility will switch to natural gas operation when the natural gas pipeline will be commissioned. The power plant’s dual-fuel engines can be operated both on liquid fuel and natural gas and could be converted to operate with future low- or zero-carbon fuels when they become available.

“Wärtsilä now has more than 400 MW of installed capacity for the cement industry in Nigeria, and we are operating three captive power plants in three different states. This successful track record clearly indicates our capabilities and highlights the added value we can deliver to our customers through our experience and expertise in supporting their operations,” comments Patrick Borstner, Director, Operations Africa at Wärtsilä Energy.

Nigeria has an increasing demand for cement for its many infrastructure projects, and there has been a domestic supply gap. With this new plant, Mangal will partly address this issue.

The partners are keen on initiating a 12MV-power generation facility, with expandable capacity. (Image source: Adobe Stock)

Independent upstream oil and gas company Invictus Energy Limited, mine operator Dallaglio Investments and power generation firm Himoinsa Southern Africa Proprietary, have signed a memorandum of understanding (MoU) to use gas extracted from the Cabora Bassa Project for power generation at the Eureka Gold Mine 

President of the Italian Republic Sergio Mattarella visited Eni facilities in Abidjan, Côte d'Ivoire. (Image source: Eni)

President of the Italian Republic Sergio Mattarella visited Eni facilities in Abidjan, Côte d'Ivoire

Analysis of samples have yielded several positive results. (Image source: Invictus Energy)

In an update on the Cabora Bassa project, Zimbabwe, Invictus Energy confirmed that Mukuyu is rich in gas 