Development work accelerates at Ntorya gas field in Tanzania
The giant Ntorya gas field development in Tanzania is anticipated to deliver vital domestic energy supplies, alleviate local energy poverty, and drive long-term industrial and economic growth for the country
Tanzanian government authorities have recognised the urgency of the project's advancement and to make sure there is no delay, an optimised timetable has been established in consultation with the joint venture partners involved in the field's development. Designed with an aim to achieve first gas production by December, the packed schedule includes critical well workovers, testing, and accelerated drilling. Fully funded field operations and pipeline infrastructure integration will prepare the site for production generation.
Aminex has reached an agreement on the sequencing and implementation of the Ntorya gas development following a meeting convened by the Tanzanian Ministry of Energy
Key stakeholders convene
Representatives of the Ministry of Energy, the Petroleum Upstream Regulatory Authority (PURA), the Tanzania Petroleum Development Corporation (TPDC), ARA Petroleum Tanzania Limited (APT), the operator of the Ruvuma PSA, and Aminex's wholly owned subsidiary, Ndovu Resources Limited (Ndovu) were present at the meeting.
While the government did not approve the operator's proposal to extend and delay the project timetable, it did confirm a revised implementation schedule with all the parties involved. This schedule comprises workover of the Ntorya-1 well (NT-1) in October, the testing of the Ntorya-2 well (NT-2) in November and the drilling of a newly planned NT-Central well (NT-C) in December.
First gas from NT-1 and NT-2 is targeted for December. Drilling of the Chikumbi-1 well (CH-1) is to proceed after NT-C is drilled. Following the change of management at ARA Petroleum LLC and a technical reappraisal of the Ntorya project, APT had proposed bringing forward NT-C, previously planned as a development well for a later phase of field development, in place of CH-1, with the drilling of CH-1 deferred. The revised implementation schedule plans to drill the NT-C first, followed by the drilling of CH-1.
It was also confirmed at the meeting that the Ntorya to Madimba pipeline will be completed in time to receive first gas from the Ntorya field in December 2026.
APT confirmed to the parties that it had all necessary funds to carry out the revised programme for the development of the Ntorya field.
The parties agreed that APT should execute the planned activities in accordance with the revised implementation schedule and without unnecessary delay. The revised programme will now be progressed through the formal Joint Venture approval process in accordance with the Joint Operating Agreement.
Economic impact of the project
Charles Santos, executive chairman of Aminex, said, "I would like to thank Dr James Mataragio, Permanent Secretary for Petroleum at the Ministry of Energy, for convening the meeting last week and for the constructive approach taken by all parties. Our focus now is on working together to implement the agreed programme and deliver first gas without further delay.
"The revised implementation programme establishes clear near-term operational milestones, targets first gas for December 2026 and provides for the drilling of a newly planned well, NT-Central, while ensuring that the CH-1 well is also drilled.
"Together, these activities form just the beginning of the development of the giant Ntorya field which is expected to deliver large volumes of gas supplies to Tanzanians, helping alleviate energy poverty, boost industrial development and fuel Tanzania's economic growth."